Developing a 400MW, gas fired, combined cycle power plant in the municipality of Kpone within the Tema industrial zone.
Posted by kaye in Company's Press Release on April 20, 2008
InfraCo is developing a 400MW, gas fired, combined cycle power plant in the municipality of Kpone within the Tema industrial zone. The project will provide urgently needed low cost, reliable and efficient thermal power to the deregulated Ghanaian power market and will become one of the main off-takers of the West African Gas Pipeline.
Partners
- Reltub Company Limited of Ghana
- Cenpower of Ghana
Location of Project

Located appr. 25 km from Accra Ghana
See Map ›
Kpone IPP – Site ›
Statement of project objectives
Primary economic benefits
- Improved access to low cost electricity in Ghana, improved usage of the West African Gas Pipeline Project.
Primary social benefits
- Access to electricity for all social sectors.
Approximate scope of project
Cost – US$500 million
Time – 2 years construction, 25 years operation
Developer in charge
Ebbe Hamilton
Pictures
InfraCo’s local partner Mr. Brew-Butler receiving the Kpone IPP Generation License from the Ghanaian Energy Commission